offshore windfarm
Preparation for installation on East Anglia ONE

ScottishPower Renewables and Macquarie’s Green Investment Group (GIG) have successfully installed every single turbine on the East Anglia ONE offshore windfarm – another major milestone for the project as it approaches completion.

Beginning in June 2019, a total of 102 Siemens Gamesa SWT-7.0-154 offshore wind turbines have been installed at the windfarm site, 43km off the Suffolk coast. Installation was undertaken by Siemens Gamesa using the Sea Installer and Sea Challenger vessels, operated by DEME.

All turbine components were pre-assembled and loaded out from Peel Ports Great Yarmouth, following ScottishPower Renewables’ £5 million co-investment in the port to prepare it for construction and marshalling activity. The components consist of 75-metre fibre glass blades, tower sections and nacelles (the head of the turbine), which have been on view along the Great Yarmouth seafront and skyline as the 90-metre-high towers were constructed on the quayside.

Each of the 306 turbine blades were manufactured by Siemens Gamesa at its specially-built factory in Hull, England; while some of the towers were produced in Machrihanish, Scotland by CSWind UK. The work that took place at Peel Ports was supported by several local companies and personnel employed by Siemens Gamesa, including Lowestoft-based Delpro Wind and CLS Global Solutions, based in Great Yarmouth.

The windfarm is already making a substantial contribution to the production of green energy, with commissioning still underway. Once fully operational, it will produce 714MW of clean energy annually – enough to power the equivalent of more than 630,000 homes*.

offshore windfarm
Final turbine installed on East Anglia ONE

As well as the successful turbine installation, ScottishPower Renewables reached a company milestone during construction, installing its 1,000thMW of offshore wind power on the East Anglia ONE site. Furthermore, Siemens Gamesa notched up the installation of their 1,000th Direct Drive offshore turbine during this project.

Charlie Jordan, East Anglia ONE Project Director at ScottishPower Renewables, said: “Successful installation of all the turbines is a tremendous achievement for the East Anglia ONE project. It brings us another step closer to completion when the windfarm will be producing the clean, renewable energy the UK needs to decarbonise and meet its pledge to reach net-zero by 2050. This project is testament to the leading role East Anglia is playing in offshore wind and is delivering tangible benefits for its people, businesses and communities – including the creation of more than 800 jobs and spending over £70 million with companies across the region.

“With COVID-19 bringing much of the economy to a standstill and affecting everyone across the UK, ensuring we have a safe and secure supply of energy is critical to supporting our vital services. This is why the continuation of this project is deemed as essential work by the Government and ourselves. The full range of people and organisations involved deserve huge credit for the work they have put into making sure it remained on track through such challenging conditions – they are a credit to the industry.”

Edward Northam, Head of GIG Europe, said: “East Anglia ONE has illustrated the role offshore wind projects can play in supporting businesses across the UK, supporting hundreds of skilled jobs in the process. We’re committed to driving the UK’s energy transition, establishing offshore wind as the backbone of the UK’s new low-carbon energy system.”

offshore windfarm
Tower of the final turbine being installed

Andrew Elmes, East Anglia ONE Senior Project Manager at Siemens Gamesa, added: “Ensuring the safety of our employees, customers and suppliers is at the forefront of all we do. We are proud to be working alongside the entire team to safely manufacture, install, and commission the turbines for East Anglia ONE. It’s been a long, challenging journey so far, with new technology, significant weather conditions, and now COVID-19 to overcome. All these factors make this milestone even more fantastic.

“Through collaboration and drawing on our expertise in offshore wind power, as well as harnessing the vast experience of the UK supply chain, we have been able to safely complete installation in good order and ensure East Anglia ONE will deliver reliable clean energy for generations to come.”

East Anglia ONE, a joint venture between ScottishPower Renewables and Macquarie’s Green Investment Group, is a £2.5 billion project and the first of four offshore windfarms ScottishPower Renewables is developing in the region. For more information about East Anglia ONE visit: www.spreastanglia.co.uk.

 

About East Anglia ONE:

East Anglia ONE comprises 102 wind turbines installed in the southern North Sea, approximately 30 miles off the coast of Suffolk. The overall investment will be in the region of £2.5 billion, and the project is planned to meet the annual electricity demands of the equivalent of over 630,000 homes*.

East Anglia ONE Offshore Windfarm project will include:

Offshore wind turbines and foundations (102 wind turbines to provide an installed capacity of 714 megawatts).

An offshore substation to collect the electricity from the turbines and transform it to a form suitable for transfer to shore.

Two offshore export cables, each around 85 km in length, to transfer the electricity to shore.

A landfall site with onshore transition pits to connect the offshore and onshore cables.

Six onshore underground cables, each of around 37 km in length, to transfer the electricity from landfall to an onshore substation.

An onshore substation adjacent to the existing substation at Bramford, Suffolk, to connect the offshore windfarm to the National Grid.

*Based on the following calculation: 714MW (installed capacity) x 0.3836 “offshore wind” average load factor (Digest of UK Energy Statistics) x 8,766 hours (hours per year)/3,781MWh (average domestic annual consumption) = 634,997 homes powered equivalent

About ScottishPower Renewables

ScottishPower Renewables is part of Iberdrola, a world leader in clean energy with an installed capacity of over 28,000MW, and the leading wind energy producer worldwide.

Responsible for progressing Iberdrola’s wind energy projects in the UK, ScottishPower Renewables also manages the development, construction and operation of offshore windfarms throughout the world and currently has 40 operational windfarm sites producing over 2,000MW.

About Green Investment Group and Macquarie Group

Green Investment Group Limited (GIG) is a specialist in green infrastructure principal investment, project delivery and the management of portfolio assets, and related services. Its track record, expertise and capability make it a global leader in green investment, dedicated to supporting the growth of the global green economy.

Initially launched by the UK Government in 2012 as the Green Investment Bank, it was the first institution of its type in the world. It was purchased by Macquarie in 2017 and combined with Macquarie Capital’s renewables team to create one of the world’s largest teams of specialist green infrastructure developers and investors. Now operating as the Green Investment Group, the business and its operating platforms have investments or operations in over 25 markets, more than 400 staff and a global development pipeline of more than 20 GW.

Across the globe, GIG has supported 16 offshore wind projects, representing over 4.5 GW of operating capacity including almost 50% of the UK’s offshore wind capacity in operations or under construction.

Macquarie Group Limited (Macquarie) is a diversified financial group providing clients with asset management and finance, banking, advisory and risk and capital solutions across debt, equity and commodities. Founded in 1969, Macquarie employs 15,704 people in 31 markets. At 30 September 2019, Macquarie had assets under management of €348.9 billion.

For more information, visit www.greeninvestmentgroup.com and www.macquarie.com.


Web Design, Domain Names, Hosting, Management and ONLINE Promotion!

Would you like a new Website design for your SMALL BUSINESS or Organisation?

We offer an ‘AFFORDABLE’ complete website design service, including domain name registrations, hosting, search engine optimisation.

We can set up sites for you to run yourself, or we manage for you.

Web design

 ‘Simple But Effective’

This is one of our latest site builds: iceniTKD.uk domain, logo, web design, hosting and promoting!

We can also publish a regular editorial for you on iceniPost.com, our online community publication, which in turn promotes your new website, this really works, and also helps get your site quickly into the highest Google rankings.

advertising

iceniPost.com has over ONE MILLION views every month.

Please email us if you would like an estimate for your new site, or wish to know more about our fully managed website services.
Email [email protected]